Piggable wyes have been
used extensively in deepwater oil and gas pipeline operations to allow cleaning
and inspection pigs and intelligent pigs access through main lines and the
laterals that tie into them. Being able to run these state-of-the-art pigs through
the wye improves the operating efficiency and the long-term integrity of the
pipeline system. Although wyes improve operations on some levels, there are
cases when operators need to run pigs counter to the normal flow direction in
the lines. This presents no problem in a pipeline with no piggable wyes, but
the internal profile at the wye fitting juncture does not permit reverse flow
pigging.
Traditional piggable wye
operations
Operators
of oil and gas pipelines wage a constant battle against the harmful effects of
internal corrosion, paraffin, and condensate accumulation. Commonly accepted
practice dictates that the operator run pipeline pigs through the line. The
pipeline product flow pushes these cleaning devices through the length of the
line. The pig maintains contact with the internal wall of the pipe, pushing
hydrates, paraffin, condensate, and other potentially harmful agents in advance
of its passage through the pipeline. Corrosive elements are removed from the
line at its termination point, enhancing the long-term integrity of the
pipeline.
Pigging
a single line is a straightforward process, requiring only that the pig be
launched from one end and pushed the length of the line using a liquid or gas
medium as the propelling force until it is captured in the pig receiver at the
end of its journey. However, pigging lateral line tie-in connections requires
that the operator pre-plan the installation of a piggable wye fitting in the
main line during the construction process. A piggable wye is a Y-shaped fitting
that has two inlets, one for each incoming pipeline, and a single outlet that
merges the flow of the two converging pipelines. The two lines converge in the
Y at an intersecting angle of 30°. This basic wye configuration was originally
tested in the 1980s and has proven to be a reliable design.
For years, the question
has been whether it would be feasible to run pigs backward through a wye from
the outlet through one of the inlets in a reverse flow pigging application.
Until now, the answer has been no.
The
internal profile of the wye at the juncture of the two pipelines would likely
cause the pig stick in the fitting. Alternatively, if the pig managed to
traverse the juncture area of the wye, there would be no way to determine which
of the two converging pipelines the pig would flow into.
Bi-directional pigging
A
recently developed product now allows pigs to run forward or backward through a
wye. The Director Wye has the unique ability to accommodate reverse flow
pigging. This new direction in piggable wye technology uses an internal
diverter sleeve that is actuated from the exterior of the wye. The diverter can
be actuated by an ROV or diver. The internal diverter sleeve rotates within the
mainline bore of the wye to direct the pig.
The open position permits
normal pigging operations that originate through the main line and/or the
lateral line that converges into the single main line downstream of the wye.
When the internal sleeve of the Director Wye is rotated to the closed position,
the barrel of the sleeve closes the access port within the wye from the lateral
line to the main line. Conventional pigging can still be conducted through the
main line in the closed position, but the diverter sleeve allows a pig to run
in the reverse flow direction through the main line as well. With the lateral
line bore closed, the pig cannot jam in the juncture of the wye and cannot
inadvertently enter the bore of the lateral line.
The Dual Director Wye
The
Director Wye had no more entered the market than an operator asked if the
design could be modified to permit bi-directional pigging through both the main
line and the lateral legs of the wye. The Dual Director Wye accomplishes this
feat through the addition of a mirror-image internal diverter sleeve in the
lateral leg of the fitting.
Like its predecessor, the
Dual Director can be used as a standard wye with both diverter sleeves in the
open position. When the main line diverter is operated to shut off access to
the lateral opening, the Dual Director also permits bi-directional pigging
through the main line. The differentiating feature of the Dual Director is that
if the mainline sleeve closes the main line and the lateral line sleeve is
open, bi-directional pigging can be accomplished through the lateral line. The
design of the dual internal diverter sleeves and the actuation system is the
same for both the Director Wye and Dual Director Wye.
Concept to reality
The
Director Wye was initially proposed to a client by means of a hand sketch on a
marker board. That rough sketch led to the final product.
An
operator planned to commission a pipeline by flushing the water from the line
using a pig from the platform to a subsea pig receiver. The plan required that
a second operation be performed to remove the subsea pig receiver and to make
the final tie-in to a wye on the pre-existing pipeline. This approach entailed
several technical and environmental difficulties and was costly in the
deepwater environment.
The
Director Wye allows the operator to make the subsea connection to the existing
pipeline first. Then, the pipeline can be dewatered by opening the valve at the
subsea tie-in point and using the pipeline product to push a pre-installed pig
in a reverse flow direction through the Director Wye all the way to the
platform. Reportedly, this innovative approach will simplify the operational
process and reduce commissioning costs for the pipeline.
Future applications
There
are other potential applications for the Director Wye, many of which offer
benefits to shallow-water and onshore operators. Potential applications for the
bi-directional piggable wye include:
- Deepwater
tie-backs: Standard practice for deepwater subsea tiebacks dictates the
installation of dual pipelines to permit roundtrip pigging of the lines.
In many cases, the dual lines are several miles long. The installation of
a Director Bi-Directional Wye would enable the operator to install a
single line and still be able to pig the system. The pig would enter the
wye in the reverse flow direction on its way to the wellhead. The internal
director sleeve would be rotated to permit the pig to enter the lateral
leg of the wye in a standard flow direction and traverse the wye on its
return journey to the platform. Eliminating the redundant flowline reduces
capital expense. This procedure also reduces the number of marine risers
on the platform to a single riser.
- Permanent
reverse flow projects: In certain cases a subsea pipeline system is
designed to accommodate a future need to use reverse flow to provide feed
gas for offshore operations from an onshore processing facility. In this
case, the wye functions as a standard wye as long as the offshore
structure can produce enough gas for its operational purposes. Once this
is no longer the case, the internal sleeve of the Director Wye can be
rotated to permit reverse flow of the product and any required pigging
operations to one or more offshore structures.
- Coiled
tubing access for deepwater risers: A Director Wye could be installed
topside in a marine riser to permit more efficient coiled tubing access.
The wye would be installed such that pigging the riser and pipeline could
follow the conventional flow. The internal director sleeve would be
rotated to close off access to the lateral leg of the wye. When coiled
tubing access is required, the internal director sleeve would be rotated
to open access to the lateral and permit the installation and withdrawal
of the coiled tubing. At the conclusion of the operation, the internal
sleeve would be rotated again to close off the tubing access lateral
opening to permit pigging of the riser once again.
- Onshore
applications: The Director Wye would permit the use of intelligent pigs
alternatively through either the main line or the lateral without
compromising piggability in either line.
source :
http://www.offshore-mag.com/articles/print/volume-67/issue-11/drilling-completion/new-direction-in-piggable-wye-technology.html
I really liked your Information. Keep up the good work. Marine pipeline repair
BalasHapus